Will the failure to lift the “subject” preclude the formation of a binding contract?
Introduction
In DHL Project & Chartering Ltd v Gemini Ocean Shipping Co Ltd
(Newcastle Express) [2022] EWHC 181 (Comm), the Commercial Court of the
High Court of England and Wales (the “Court”) has set aside an
arbitration award in a charterparty dispute on the basis that the arbitration
tribunal had no jurisdiction to rule since no binding contract (nor arbitration
agreement) was concluded when the fixture was expressed to be subject and such
subject was not lifted.
Background
In August 2020,
the Claimants (the “Charterers”) and the Defendants (the “Owners”)
negotiated the terms of a fixture through the intermediary of a broker. The
Owners intended the vessel (the “Vessel”) to be inspected by Rightship, a third party maritime due diligence organisation. In the
email sent by the chartering broker to the Charterers regarding a fixture
“recap”, there was a “subject” provision (the “Subject”) in bold context
at the start of the email in the following wordings:
“SUBJECT
SHIPPER/RECEIVERS APPROVAL WITHIN ONE WORKING DAY AFTER FIXING MAIN TERMS &
RECEIPT OF ALL REQUIRED”
Later, the
shipper pressed for a faster schedule for completion of inspection by
Rightship, and ultimately decided that it did not want to wait for the Vessel.
The Charterers communicated to the Owners in September 2020 that the Vessel was
free as the Charterers would not be lifting the Subject and the deal had fallen
through.
Arbitration
The Owners
commenced arbitration proceedings against the Charterers for repudiation of the
charterparty. The arbitrator (the “Arbitrator”) held that the Subject should
be read together with other clause of the proforma charter such that the
charterparty provided that:
“the approval of
the Vessel was “subject shippers/receivers’ approval within one working day
after fixing main terms and receipt of all required/corrected
certificates/documents such approval not to be unreasonabl[y] withheld.”
The Arbitrator was of the opinion that the approval was unreasonably
withheld and so awarded damages for repudiation to the
Owners (the “Arbitral Award”).
Issue
The Charterers sought
to challenge the Arbitral Award on the basis that there was no binding contract
nor arbitration agreement concluded between the parties. The Charterers argued that
although the parties had agreed upon all the essential terms of a fixture, the
agreement was on “subjects” or “subs” – it was subject to shipper or receivers’
approval which was never lifted. The Subject showed an intention not to create
legal relations unless and until the Subject being lifted. Therefore, the
Charterers contended that the Arbitrator had no jurisdiction to make the
Arbitral Award and applied to the Court to set aside the Arbitral Award under section
67 of the Arbitration Act 1996.
In contrast, the
Owners argued that the parties had clearly and expressly agreed to arbitration
and so there was a binding arbitration agreement. By the doctrine of
“separability”, the arbitration agreement was distinct from
the underlying charter, therefore, the invalidity of the contract would not
impugn the enforceability of the arbitration agreement. Therefore, the
Arbitrator had the substantive jurisdiction to decide whether or not there was
a binding contract.
Legal
principles
On the effect
of the Subject, the Court held that it qualified everything that followed which
naturally included the arbitration clause. The Court made
reference to a very similar decision of Foxton J in Nautica Marine Ltd v
Trafigura Trading LLC [2020] EWHC 1986 (Comm), where it was noted that:
1.
There is a particular feature of negotiations for the conclusion of
contracts for the employment of ships – “subjects” or “subs” are pre-conditions
to contract which remain outstanding, therefore, conclusion of such a binding
contract is dependent on the agreement of the relevant party or parties to lift
(i.e. remove) the subjects.
2.
Unless and until the condition precedent is satisfied, no binding
contract is concluded.
The Court ruled
that the Subject fell into the category described by Foxton J. The Court noted that
the commercial purpose of such subject was obvious – the
Charterers did not wish to make a binding contract at all unless and until both the shipper and receiver’s approval of the
Vessel was given. A charterer may wish to reserve its position fully. The Court
acknowledged that this was the well-recognised practice in the chartering
market.
Accordingly, the
Court found that there was nothing in the documents which could support the
suggestion that there was any approval of the Vessel by the shippers nor the
receivers at any stage. The Court took the view that the correspondence
exchanged by the parties cannot be read as the communication of shippers’
approval (either by the shippers themselves or by the Charterers) since it was
clear that any approval would not be given prior to the result of the Rightship
inspection being known. The Court held that the Subject was not lifted, and that
the Owners were aware that the shipper would not give approval until the
Rightship inspection had been satisfactorily concluded.
On the Owners’
argument of separability, the Court noted that whether a contract and an
arbitration agreement may stand or fall together depends upon the facts
and the particular argument advanced. However, in this case, the arbitration
agreement was not separable from the charter and therefore the Subject is also
applicable to the arbitration agreement for a number of reasons:
1.
As the effect of the Subject was to negate the Charterers’ intention to
enter into any contract at all, unless and until it was lifted, there was no
reason for the Charterers intending to make any contractual commitment to
arbitration.
2.
The natural interpretation of the positioning and use of bold text of
the Subject in the recap indicated that the Subject qualified everything that
followed, including the arbitration agreement.
3.
The arbitration agreement was not regarded as a mini-agreement separated
from the main agreement. Instead, it was part and parcel of the proposed
agreement as a whole. The arbitration agreement was part of the bundle of
rights and obligations under negotiation, and all of those rights and
obligations were subject to the Subject.
Accordingly,
the Court held that there was no operative arbitration agreement concluded and
so the Arbitrator had no jurisdiction to give the Arbitral Award. The Court
ruled in favour of the Charterers on section 67 application and set aside the
Arbitral Award.
Key
takeaways
This case serves
as a reminder on the use of subjects or conditions in contractual negotiations,
especially in the charterparty context. Courts will generally
hold that “subjects” indicate a pre-condition which, until the subjects being
“lifted”, will preclude a binding contract. Therefore, in drafting the charterparty,
one should make it clear as to what must be done, when and by whom, to lift
such subjects. If one intends for the issue of whether subjects or approvals had
been unreasonably withheld to be resolved by arbitration, clear and unequivocal
wordings must be used.
For enquiries, please feel free to contact us at: |
E: shipping@onc.hk T:
(852) 2810 1212 19th Floor, Three Exchange Square, 8 Connaught
Place, Central, Hong Kong |
Important: The law and procedure on this subject are very specialised and complicated. This article is just a very general outline for
reference and cannot be relied upon as legal advice in any individual case. If
any advice or assistance is needed, please contact our solicitors. |
Published by ONC Lawyers © 2022 |