Can Court Proceedings on a Statutory Claim be Stayed for Arbitration?
Introduction
In Chevalier (Construction) Co Ltd v.
Universal Aluminium Industries Ltd HCA 2338/2013, the
Court of First Instance ordered a stay of the court proceedings over a claim
based upon the Employment Ordinance (Cap. 57) and held that the dispute should
be resolved by way of arbitration.
Background
In Chevalier (Construction) Co Ltd v.
Universal Aluminium Industries Ltd HCA 2338/2013, the
Plaintiff was the principal contractor and the Defendant was the sub-contractor
for two projects in the New Territories, namely, “the Tuen Mun Project” and
“the Tai Po Project”.
The Defendant completed its work under the sub-contract
for the Tuen Mun Project and submitted a final account to the Plaintiff, in
excess of around HK$10.5 million, but the Plaintiff refused to pay the
Defendant.
In May 2013, the Plaintiff formally terminated the
Defendant’s sub-contract for the Tai Po Project. The Defendant claimed that the
Plaintiff owed it about HK$20 million. Because of the Plaintiff’s failure to
make such payments, the Defendant had been unable to pay the wages due to its
employees and sub-contractors in respect of both projects.
Subsequently, the parties agreed that the Plaintiff would
make direct payments to the Defendant’s employees and sub-contractors to
satisfy its obligations under section 43C of the Employment Ordinance (Cap. 57)
(the “Ordinance”). The payments would then
set off any payments found to be due to the Defendant.
Both parties then served a Notice of Arbitration
referring the dispute over the two projects to arbitration respectively.
Meanwhile, the Plaintiff commenced court proceedings against the Defendant,
claiming reimbursement of some HK$2 million, being the wages paid to the
Defendant’s employees and sub-contractors under the Ordinance.
The Dispute Clause
The Defendant took out an application to stay the proceedings on the basis that
the parties had agreed to refer the matters at dispute to arbitration.
The relevant dispute clause in the sub-contracts stated
that “[the dispute] shall be referred to and resolved by arbitration in
accordance with Part II of the Arbitration Ordinance of Hong Kong” (the “Clause”).
The Plaintiff alleged that the statutory claim under
which the payments were made on behalf of the Defendant fell outside the scope
of the Clause. It was further argued that even a liberal and broad construction
of the Clause would not embrace a claim based upon the Ordinance.
The Court cited Lord Hoffmann’s decision in the UK case
of Fiona Trust and Holding Corporation
v. Privalov (2008) 2 Lloyds Reports, page 254. In Fiona Trust, the
House of Lords held that the construction of an arbitration clause should start
from the assumption that the parties, as rational businessmen, are likely to
have intended any dispute arising out of the relationship into which they have
entered (or purported to enter) to be decided by the arbitral tribunal. The
clause should be construed in accordance with this presumption, unless the
language makes it clear that certain questions were intended to be excluded
from arbitration.
Court’s Analysis
The Court noted that, the statutory claim was triggered by the Defendant’s
inability as sub-contractor to pay wages, which was allegedly due to the
Plaintiff’s failure to pay the Defendant in accordance with the sub-contracts.
The payments made by the Plaintiff under the Ordinance were inextricably
involved with the dispute between the parties arising out of the sub-contracts.
Therefore, it was wholly artificial to compartmentalize the Plaintiff’s claim
for reimbursement.
When Would a Stay Application be Granted?
The Court recounted and answered the following four questions when considering the
application:
1. Was there an arbitration agreement between
the parties?
Answer: Yes.
2. Was the Clause capable of being performed?
Answer: Yes, it was distinct, all-embracing and excluded
no form or subject matter of dispute.
3. Was there in reality a dispute or difference
between the parties?
Answer: Decidedly so and its nature was quite clear.
4. Was the dispute or difference between the
parties within the ambit of the Clause?
Answer: It was and the payment under the Ordinance was
one aspect of it. The amount was not disputed. It fell to be decided,
ultimately according to the findings in respect of the core dispute between the
parties. To exclude what had been described as a statutory claim from the ambit
of arbitration would be an illiberal and constricting interpretation of the
Clause.
Decision
To determine whether it is appropriate to stay the proceedings, the Court
concentrated on the ambit of the Clause and paid due regard to the terminology
as well as the parties’ intentions. Since the language of the Clause excluded
no subject matter of dispute, the Court expressed that the Plaintiff should
never have commenced proceedings to seek reimbursement, especially when both
parties had triggered the reference to arbitration under the Clause by the
Notice of Arbitration. Accordingly, a stay of proceedings was ordered in favour
of arbitration.
Conclusion
Where the parties intend to exclude a certain subject matter of dispute from
arbitration, this must be clearly reflected in the arbitration clause. If they
fail to do so, any dispute arising out of the contract would have to be
resolved by arbitration. The Court has jurisdiction to stay the proceedings for
arbitration even after one party has initiated legal action against the other.
For enquiries,
please feel free to contact us at: |
E: ldr@onc.hk
T: (852) 2810 1212 19th Floor, Three
Exchange Square, 8 Connaught Place, Central, Hong Kong |
Important: The law and procedure on this subject are very specialised and
complicated. This article is just a very general outline for reference and
cannot be relied upon as legal advice in any individual case. If any advice
or assistance is needed, please contact our solicitors. |