Filter
Back

How to interpret a LDs clause when the contract contains conflicting and inconsistent information?

2022-08-26

Introduction

As previously discussed in our newsletter article “The past, present, future of liquidated damages in Hong Kong“, it is common practice for parties to include a liquidated damages (“LDs”) clause in commercial contracts to stipulate the amount of damages payable by the defaulting party in the event of a breach of contract. In a construction contract, LDs usually relate to the contractor failing to achieve practical completion by the completion date set out in the contract.

However, in practice, disputes often arise on the construction and interpretation of the LDs provision. In Buckingham Group Contracting Ltd v Peel L&P Investments and Property Ltd [2022] EWHC 1842 (TCC), the Court shed some light on how to interpret a LDs clause when the contract contains conflicting and inconsistent information.

Background

Buckingham Group Contracting Ltd (“Buckingham”) was engaged by Peel L&P Investments and Property Ltd (“Peel”) to design and construct the production building and certain works for a project for the construction of a new plant at Ellesmere Port in Merseyside (the “Works”) pursuant to a written agreement dated 29 January 2018 (the “Contract”). The Contract was based on a JCT standard form contract together with a schedule of bespoke amendments (the “Schedule of Amendments”).

The Contract expressly stated that the Schedule of Amendments form part of the Contract and in case of any differences between the Schedule and the JCT standard form contract, the former is to prevail.

According to the Contract Particulars of the Contract, the completion date was 1 October 2018 (the “Contract Particulars Completion Date”) and the contract sum was £26,164,049.28 (the “Contract Particulars Contract Sum”). On one hand there is a clause 2.29 concerning LDs for delay in completing the Works, on the other hand, a bespoke clause 2.29A concerning LDs for failure to achieve “Milestone Dates” was also inserted by the Schedule of Amendments. It provides, inter alia, that:

2.29A .1 If the Contractor fails to complete the works necessary to reach a Milestone Date the Employer may give notice to the Contractor that:

.1 he requires the Contractor to pay liquidated damages at the rate stated Schedule 10 or lesser rate stated in the notice, in which event the Employer may recover the same as a debt; and/or

.2 that he will withhold or deduct liquidated damages at the rate stated in Schedule 10 or at such lesser stated rate, from sums due to the Contractor.”

Schedule 10 contained a table setting out a list of milestone dates, of which the seventh Milestone Date for Practical Completion was identified as 30 November 2018 (the “Schedule 10 Completion Date”). It also contained a proposed contract sum of £25,710,050.28 (the “Schedule 10 Contract Sum”) (which is different from the Contract Particulars Contract Sum), two sets of daily rates for LDs, two sets of weekly rates for LDs and a cap on maximum LDs in the sum of £1,928,253.77.

Furthermore, it expressly stated that:-

“If there is any conflict or inconsistency between the wording of this schedule and clause 2.29 the wording of this schedule shall take precedence.”

The dispute

The Works were significantly delayed and parties were in dispute as to the responsibility for those delays. Buckingham then commenced proceedings against Peel, seeking declarations that the provisions in respect of LDs were void for uncertainty and that the cap on the LDs also operated as a cap on their liability for general damages.

Buckingham argued that the LDs provisions were void and thus unenforceable due to the following reasons:

1.       The Contract Particulars Completion Date was 1 October 2018, whereas the Schedule 10 Completion Date was 30 November 2018;

2.       Schedule 10 contains two sets of rates and it is impossible to discern which set the parties intended to apply;

3.       There were two sums contained in the Contract, i.e. the Contract Particulars Contract Sum of £26,164,049.28 and the Schedule 10 Contract Sum of £25,710.050.28;

4.       Schedule 10 failed to provide a scheme in respect of sectional completion/partial possession.

Decisions

When considering whether the LDs provisions were void and thus unenforceable, the Court examined and re-affirmed some decisions made by other courts in previous cases. As summarised in paragraph 39 of the judgement:-

“the court is reluctant to hold a provision in a contract is void for uncertainty and if it is open to the court to find an interpretation which gives effect to the parties’ intentions, then it will do so. It is only if the court cannot reach any conclusion as to what was in the minds of the parties or where it is unsafe to prefer one possible meaning to other equally possible meanings that the provision would be void.”

Different completion dates

In respect of the two different completion dates, the Court concluded that by choosing to include a bespoke milestone date regime in Schedule 10, which actually included a date for practical completion of the whole of the Works and LDs in respect thereof, the parties must have intended for that clause to operate as the sole regime in this respect. The bespoke regime prevails. In the circumstance, liability would arise when the contractor failed to meet the milestone dates, not the Contract Particulars Completion Date.

Different sets of rates

For the issue of two sets of rates described in Schedule 10, the Court allowed Peel to rely on the evidence of a witness to explain the background to Schedule 10. Notwithstanding Buckingham had objected to the relevance of the witness evidence on the grounds that it was evidence of negotiations, the Court still found that it was appropriate to take into account the factual background for the purpose of ascertaining parties’ intention. The Court concluded that it was “plain that the parties had (perhaps unwisely) taken a short cut by copying and pasting the entire table into Schedule 10 without removing those parts of it which described it as a proposal”. Since parties had executed the entire agreement as a deed, the parties must have intended the table to have had legal effect. In respect of the two sets of rates, the Court found that it is perfectly possible to rule that the right hand set of columns was the only relevant one.

Different contract sums

Regarding the conflicting contract sums issue, the Court accepted Peel’s submissions and found that it was obvious that the LDs table within Schedule 10 was initially drawn up as a proposal. Despite the contract sum being changed after the table was prepared, the parties nonetheless included the table in that form and the parties clearly intended to adopt the weekly LDs rates as calculated in Schedule 10.

Sectional completion

Lastly, the Court also rejected Buckingham’s submissions on how Schedule 10 was unenforceable for its failure to provide a workable scheme in respect of partial possession. The Court was of the view that the Contract did not provide for sectional completion. In fact, “on multiple occasions within the Contract Particulars they stated ‘Sections do not apply’”. Although there are descriptions within in the table of “sectional milestones” in Schedule 10, this does not turn them into Sections. For a more detailed discussion on the relationship between sectional completion and LDs, please refer to our earlier article “One of the burning questions in construction project – Are you entitled to reduction of liquidated damages upon sectional completion?

To conclude, it was held that the provisions were therefore certain and enforceable.

Takeaway

Poorly drafted LDs provisions may result in disputes in the future. In the present case, the Court confirmed that they are reluctant to hold that LDs provisions are void for uncertainty if a clear interpretation can be deduced. As such, it is vitally important to ensure the contract terms in respect of LDs are well drafted for the purpose of avoiding inconsistencies and ambiguities and mitigating legal risks.

 


For enquiries, please feel free to contact us at:

E: construction@onc.hk                                                     T: (852) 2810 1212
W:
www.onc.hk                                                                    F: (852) 2804 6311

19th Floor, Three Exchange Square, 8 Connaught Place, Central, Hong Kong

Important: The law and procedure on this subject are very specialised and complicated. This article is just a very general outline for reference and cannot be relied upon as legal advice in any individual case. If any advice or assistance is needed, please contact our solicitors.

Published by ONC Lawyers © 2022


Back to top