Filter
Back

Do refund guarantees under a shipbuilding contract cover restitution and reliance loss claims?

2023-01-31

Introduction

In Havila Kystruten AS v Abarca Companhia De Seguros, SA [2022] EWHC 3196, the Commercial Court of the High Court of England and Wales (the “Court”) has ruled that the buyer under shipbuilding contract is entitled to terminate on various grounds and that the buyer can recover pre-paid instalmants as reliance loss from the refund guarantees. In addition, a provision in the shipbuilding contract requiring the buyer to provide “a written committed statement of its financing” for the vessels was held not to require full loan documentation to have been executed.

Background

This case concern the termination of two shipbuilding contracts dated 10 April 2018 (the “Shipbuilding Contracts”), entered into between Havila Kystruten AS (“Havila”), as the buyer and Hijos de J. Barreras SA (the “Yard”), as the shipbuilder, for the design and build of two coastal passenger vessels for a price of €108 million per vessel. The Yard wished to terminate the Shipbuilding Contracts on 24 November 2019 on the grounds that Havila had failed to comply with an obligation arising under addenda to the Shipbuilding Contracts (the “Addenda”) to provide a written committed statement of its financing for the vessels and no other financial arrangement shall be provided by Havila in order to avoid termination of the Shipbuilding Contracts. The Yard seeks (i) the payment of two instalments which it claimed to have fallen due from Havila prior to termination; and (ii) damages.

Havila asserted that the Yard was not entitled to terminate under the abovementioned provisions. Instead, Havila gave notice to terminate the Shipbuilding Contracts on 11 February 2020 and claimed (i) the recovery of three instalments (in the aggregate sum of €18.4 million per vessel); and (ii) the same sums from Abarca Companhia de Seguros SA (“Abarca”) under a series of six insurance bonds dated 1 March, 30 April and 27 May 2019 (the “Bonds”). The Bonds provided security to Havila in the event of termination of the Shipbuilding Contracts and a claim by Havila to recover instalments it had paid to the Yard.

The issues

The Court has considered the following issues when deciding which party can terminate the Shipbuilding Contracts:

1.       whether the Yard was entitled to terminate the Shipbuilding Contracts for the breach of Havila’s obligations under the Addenda to the Shipbuilding Contracts;

 

2.       whether the Yard waived any such right;

 

3.       if the Yard did not validly terminate the Shipbuilding Contracts, whether Havila was entitled to terminate the same on the basis that (i) the Yard’s purported termination was a repudiatory act that Havila accepted; (ii) the vessels would not be completed within a certain days of the delivery dates pursuant to Article IV.1(d) of the Shipbuilding Contracts; and (iii) pursuant to Article XII.3 of the Shipbuilding Contracts, the Yard’s application for judicial dissolution on 26 November 2019 had rendered Havila the right to terminate;

 

4.       whether the Bonds issued by Abarca are in the nature of ‘on demand’ bonds, and whether they correspond to a damages claim following termination by Havila of the Shipbuilding Contracts at common law; and

 

5.       if the Yard was entitled to terminate the Shipbuilding Contracts, whether it is entitled to claim damages from Havila for wasted expenditure.


Whether the Yard was entitled to terminate the Shipbuilding Contracts

The Court held that the Yard was not entitled to terminate the Shipbuilding Contracts and claimed damages from Havila for wasted expenditure. The Court explained that the ordinary meaning of a written committed statement is a written statement of the bank’s commitment to lend, whereby the bank has given an “in principle” indication that it will lend on specified terms but without entering into any legally binding agreement. As such, the Court accepted that the issue of a term sheet by a bank in general represents an important degree of commercial commitment to the proposed transaction. The Court further held that the Yard was entitled to terminate the Shipbuilding Contracts under the terms of the Addenda if committed financing was unavailable, provided that the Yard had negotiated with Havila in good faith and concluded after 14 days that there was no alternative financial arrangement could be provided by Havila. Yet, no conclusion was reached by the parties and therefore the right to terminate did not arise.

Whether the Yard has waived any right to terminate

The Court held that even if the right to terminate had arisen, the Yard would have waived the same by failing to terminate the Shipbuilding Contracts within a reasonable time given that the Yard had engaged in ongoing discussions which indicated a continuation of the Shipbuilding Contracts with Havila.

Whether Havila was entitled to terminate the Shipbuilding Contracts

The Court held that Havila was entitled to terminate the Shipbuilding Contracts. Havila submitted that the instalments could be recovered as expenditure wasted in reliance on the Shipbuilding Contracts. On the other hand, the Yard argued that the price paid to a contractual counterparty was not regarded as reliance loss but a claim for restitution and could be recovered only in the event of total failure of consideration. The Court concluded that it would be wrong in principle for the innocent party to be left without a remedy and for the wrongdoer to be able to retain the price merely on the basis that they had provided some degree of contractual performance. 

Article IV.1(d) of the Shipbuilding Contracts provided that if it can be established beyond any reasonable doubt that the vessels will be delayed for more than 180 days or for a force majeure delay of 270 days, Havila shall have a right to terminate the Shipbuilding Contracts. As the Yard had sent the termination notice on 24 November 2019 to Havila, it was clear beyond any reasonable doubt that the Yard was not going to complete the vessels at all.

The Court also upheld Havila’s right to terminate the Shipbuilding Contracts pursuant to Article XII.3 of the Shipbuilding Contracts as the Yard had commenced judicial dissolution proceedings, even though the petition for judicial dissolution was rejected afterwards.

Havila’s claims under the Bonds

The Court construed that the Bonds are demand bonds given that payment by Abarca was due against production of stipulated documents without the need for Havila to separately prove an underlying unsatisfied liability of the Yard. The Court rejected Abarca’s submission that the Bonds did not cover termination at common law for repudiatory breach. The key provisions of the Bonds cover cases where Havila is entitled to recover an amount equal to those instalments by way of damages. Therefore, it is broad enough to cover an obligation to pay damages in the amount of the instalments and the Bonds cover a liability on the Yard to refund the instalments to Havila including by way of a liability for damages.

Key takeaways

This case puts beyond doubt that refund guarantees expressed to secure repayment of the buyer’s instalments can secure a claim in restitution or for reliance loss for such sums following a termination for repudiatory breach at common law and not just for express contractual termination. As such, the decision has provided a more complete protection to buyers in shipbuilding contracts.

 

 


For enquiries, please feel free to contact us at:

E: shipping@onc.hk                                                           T: (852) 2810 1212
W:
www.onc.hk                                                                    F: (852) 2804 6311

19th Floor, Three Exchange Square, 8 Connaught Place, Central, Hong Kong

Important: The law and procedure on this subject are very specialised and complicated. This article is just a very general outline for reference and cannot be relied upon as legal advice in any individual case. If any advice or assistance is needed, please contact our solicitors.

Published by ONC Lawyers © 2023


Our People

Sherman Yan
Sherman Yan
Managing Partner
Eric Woo
Eric Woo
Partner
Sherman Yan
Sherman Yan
Managing Partner
Eric Woo
Eric Woo
Partner
Back to top