Is an alternative dispute resolution clause considered a condition precedent to the commencement of litigation?
Introduction
In the recent case
of Children’s ARK Partnerships Limited
v Kajima Construction Europe (UK) Limited, Kajima Europe Limited [2022] EWHC 1595 (TCC), the English Technology and
Construction Court (the “Court”)
held that even though a dispute resolution procedure clause (“DRP clause”) gave rise to a condition
precedent to the commencement of litigation, the DRP clause in the current case
was unenforceable as the wordings were neither clear nor certain.
Background
In 2004, Children’s Ark Partnerships Limited (the “Claimant”) entered into a construction contract (the “Construction Contract”) with Kajima
Construction Europe (UK) Limited (the “Kajima
Construction”) for the design, construction and commissioning of the Royal
Alexandra Hospital for Sick Children in Brighton (the “Hospital”). The Claimant had signed a Project Agreement of even
date with the NHS Hospital Trust for the design, building and financing of the
redevelopment of the Hospital.
Clause 9.7 of the Construction Contract provided that no claim, action
or proceedings shall be commenced against Kajima Construction after the expiry
of twelve years from the Actual Completion Date (i.e. 2 April 2007). Despite
the fact that such limitation period would have expired on 2 April 2019, the
parties agreed to a standstill agreement dated 29 March 2019 (which was subsequently varied on four occasions: 7 April 2020, 29
March 2021, 28 June 2021 and 27 September 2021) due
to the ongoing remedial works carried out by Kajima Construction since December
2018. As such, the limitation period was extended to 29 December 2021.
The Claimant initiated legal proceedings on 21 December 2021 and issued
an application seeking a stay of proceedings in order to pursue the DRP clause.
On the same day, Kajima Construction made an application under Rule 11 of the
Civil Procedure Rules (“CPR”)[1] to
strike out/set aside the Claimant’s claim on the grounds of failure to comply
with a contractual alternative dispute resolution provision, which was argued
to be a condition precedent before commencing legal proceedings.
The issues for the Court to decide were:
1. whether a DRP clause gave rise to a condition precedent or whether
it was a mandatory jurisdictional provision;
2. whether the provisions of DRP clauses were enforceable;
3. if enforceable, whether the provisions of DRP clauses were complied
with by the Claimant in advance of issuing proceedings;
4. whether Rule 11(1) of CPR was engaged; and
5. if Rule 11(1) of CPR was engaged, how should the Court exercise its
discretion.
Decision
The Court considered Ohpen
Operations UK Ltd v Invesco Fund Managers Ltd [2019] BLR 576 (“Ohpen”),
which listed out the circumstances that the court may stay proceedings where a
party seeks to enforce an alternative dispute resolution provision, including
(i) the obligation must be expressed clearly as a condition precedent to court
proceedings; (ii) the DRP clause must be clear and certain by reference to
objective criteria; and (iii) the court has discretion to stay proceedings
which were commenced in breach of an enforceable dispute resolution agreement.
Although the
Court held that complying with a DRP clause was a condition precedent with
clauses providing for a sequence which must be followed before legal
proceedings can be commenced, the Court, however, disagreed with the finding in
Ohpen based on the reason that
an obligation must be expressed clearly
as a condition precedent before the Court will stay proceedings.
In this regards, the Court confirmed in paragraph 58 of the current judgment:-
“The Court’s task in interpreting the Construction Contract
is to apply the ordinary and well known principles of contractual
interpretation, i.e. to ascertain the objective meaning of the language used by
the parties to express their agreement.
It is not necessary for the words ‘condition precedent’ to
be used, as long as ‘the words used are clear that the right to commence
proceedings is subject to the failure of the dispute resolution procedure’. It
is necessary to have more than a mere statement that compliance with dispute
resolution procedure is mandatory.”
Furthermore, the Court reiterated that it has an inherent jurisdiction
to stay proceedings for the enforcement of alternative dispute resolution when
the clause in question creates a mandatory obligation and where it is
enforceable.
In addition, the Court outlined the following reasons why the DRP clause
in the current case was unenforceable as it was neither clear nor certain:
1. there was no meaningful description of the process to be followed
regarding the alternative dispute resolution;
2. there was no unequivocal commitment to engage in any particular alternative
dispute resolution procedure. There was a lack of certainty and it was
unclear how a court was to decide which party was in compliance or breach;
3. the Liaison Committee was to comprise only of representatives from
Brighton and Sussex University NHS Trust and from the Claimant, with a
provision for others to be invited to attend. Since there was no representation
on the committee by the defendants, the process would not have final or binding
effect; and
4. it was unclear when the condition precedent is satisfied and when
the process was intended to come to an end.
Based on the above reasons, the Court considered
that the strike out and abuse of process applications failed.
Takeaway
The above English decision serves as a reminder to the employers /
contractors to take heed in the course of negotiating terms and conditions of
construction contract. In particular, for the condition precedent for applying
for time extension, claims for loss of expenses and/or dispute resolution
mechanism, the wordings must be clear and certain. With that being said, the
Court of Appeal has recently granted permission to appeal the Court’s decision
in the current case. Therefore, the final outcome of whether an alternative
dispute resolution clause is considered to be a condition precedent before the
commencement of legal proceedings is yet to be seen.
For enquiries,
please feel free to contact us at: |
E: construction@onc.hk T: (852) 2810
1212 19th Floor, Three Exchange Square, 8 Connaught
Place, Central, Hong Kong |
Important: The law and procedure on
this subject are very specialised and
complicated. This article is just a very general outline for reference and
cannot be relied upon as legal advice in any individual case. If any advice
or assistance is needed, please contact our solicitors. |
Published by ONC Lawyers © 2022 |
[1] Rule 11(1) of CPR
states that “a defendant who wishes to
(a) dispute the court’s jurisdiction to try the claim or (b) argue that the
court should not exercise its jurisdiction may apply to the court for an order
declaring that it has no such jurisdiction or should not exercise any
jurisdiction which it may have.”